Project Name
Rajiv Gandhi Gramin Vidyutikaran Yojana
Location
Raibareily
Duration
36 Months
Approx Value
6800 Lacs
Home   ::   Projects    ::   Rural Electrification  ::  RGGVY Project, PGCIL, Raibareily
RGGVY Project, PGCIL, Raibareily
Rural Electrification works – Supply and installation of materials for 11 KV HT lines, distribution transformers, AB cable and reconductoring of 11 KV line, Supply and installation Materials for LT line using 1 phase (1x16+25) sq.mm aerial bunched cable with 45 meters span, Materials for pole mounted distribution transformers (1ph 25 KA & 1 ph 16 KVA), Service connections ; Supply & erection of materials for 33 / 11 KV new substation works, augmentation of existing sub-station works, 33 KV line bays and 33 KV lines, break up type test charges etc. replacement of old conductor with rabbit on existing 11 KV HT lines, stringing of conductor, erection of pole mounted distribution transformers, reconducting of existing 33 KV line with AAAC equipment to ACSR DOG conductor, etc.

33 KV substations commissioned : 13 Nos.
Station transformers commissioned : 3 Nos.
Power transformers commissioned : 14 Nos.
33 KV transmission line erected & charged : 240 KM
11 KV transmission line erected & charged : 2,